Two tools stop that from happening: enough spinning reserve on the running engines, and a load shedding scheme that drops the right loads quickly when reserve is not enough. This article explains how mine station operators size reserve, how a staged scheme is built and how both are tested before a real fault tests them instead.
Why an island grid behaves differently
On a large interconnected grid a single generator trip is a small event, because hundreds of machines share the loss and their combined inertia slows any change in frequency. A mine network fed by six or eight medium-speed engines has very little stored rotating energy, and each engine may carry 12 to 18 percent of the total load.
The result is that frequency falls fast after a trip, often several hertz in a few seconds, unless the surviving engines respond at once. Large motor loads such as mill drives, conveyors and ventilation fans also react to falling frequency and voltage, which can make recovery harder rather than easier.
What spinning reserve means at a mine
Spinning reserve is the unused output on engines that are already running and synchronised. If eight 8 MW engines are online carrying 48 MW between them, each runs at 6 MW and the station holds 16 MW of reserve. Any engine that trips takes 6 MW with it, and the other seven must share that extra load.
Reserve held on engines that are stopped, even on hot standby, does not count for the first seconds after a trip. A cold HFO set may need several minutes to start, warm through and synchronise, so it supports recovery afterwards but cannot stop the initial frequency drop.
Sizing reserve against the largest unit
The common starting rule is that running reserve must at least equal the output of the largest loaded engine, so that a single trip can be covered without shedding anything. Some mines add a margin for the largest single motor start, because a mill or hoist starting at the wrong moment uses the same headroom.
A simple check helps. With 48 MW of load and 8 MW engines, seven units would run at about 86 percent, leaving roughly 8 MW of reserve, which just covers one 6.9 MW engine trip. Running eight units lowers the loading to 75 percent and gives comfortable cover, at the cost of more engines in service.
The fuel cost of carrying reserve
Reserve is not free. Each extra engine online burns fuel to turn itself and runs further from its best efficiency point, so specific fuel consumption rises a little across the whole station. Over a year that difference can add up to hundreds of tonnes of HFO on a mid-sized plant.
That is why reserve policy should be written down and agreed with the mine rather than left to each shift. Our article on adding engines to a mine station in stages explains how the installed engine count is chosen so that the station can carry its reserve without long periods of very light running.
How a staged load shedding scheme works
When reserve is not enough, for example after two engines trip together or during a period when units are out for maintenance, under-frequency relays disconnect blocks of load in a set order. A typical mine scheme has three to five stages, each triggered at a lower frequency or after a set time below a threshold.
- Stage 1: loads that can stop without harm, such as office air conditioning, workshop compressors and camp water heating.
- Stage 2: process loads that can restart easily, such as some flotation cells, crushers or conveyor sections.
- Stage 3: large drives such as a ball mill, accepting a process upset to save the grid.
- Final stage: everything except life-safety and dewatering loads.
Loads that must never be shed
Every mine has loads that should stay on whatever happens: underground ventilation, dewatering pumps, hoists carrying people, refuge chambers, the station’s own auxiliaries and the control system. These sit at the top of the priority list and are fed from feeders that no shedding relay can open.
Hoist and ventilation duties deserve particular care because they are large and safety-critical at the same time. Our guide to powering hoists and main fans covers how those drives are fed and protected, and the shedding scheme must be designed around them rather than the other way round.
How fast HFO engines can pick up load
Medium-speed engines running on heavy fuel accept sudden load in steps rather than all at once. The maker’s load acceptance curve shows how much extra load an engine can take in one step without a dangerous dip in speed, and this figure is lower at high starting loads and with a slow turbocharger response.
Station designers use these curves to check that the surviving engines can share a trip. If they cannot, the first shedding stage must act quickly enough to close the gap. Some stations add a battery system that injects power in the first second, giving the engines time to respond and reducing how often load has to be dropped. Our note on how engines and turbines respond to load steps explains why prime mover choice also shapes this part of the design.
Setting the relays and protection
Shedding thresholds must sit above the point where engine protection trips the generators on under-frequency, otherwise the station protects itself by shutting down before the scheme has helped. A typical layout leaves a clear margin between the final shedding stage and the generator under-frequency trip.
Rate-of-change-of-frequency relays can speed up the first stage on very small grids, but they need careful settings to avoid nuisance trips during motor starts. Settings should be studied with a dynamic model of the network and reviewed whenever engines, large motors or feeders are added.
Testing, drills and operating rules
A scheme that has never operated cannot be trusted. Commissioning should include secondary injection of every relay, a check that each stage opens the right breakers and, where the mine agrees, a planned trip of one engine under controlled conditions to confirm that the station rides through.
Afterwards, the reserve rule, the shedding list and the restoration order should be part of the operating manual and part of shift handover. Contractors running the plant under an O&M agreement for the station usually report reserve compliance and every shedding event each month, which gives the mine an early warning when load growth starts to eat into the margin.
About the authors
This guide comes from the USP&E protection engineers and station operators who design and run island-mode HFO power stations for African mines. USP&E is an EPC and O&M contractor, not a broker, with 150+ power projects in 45+ countries, 25,000 MW contracted since 2002 and 24+ years in the field. Our reference on building and operating HFO stations sets out how reserve and protection fit into the wider plant design.
Offices: Colorado Springs (1755 Telstar Dr, Suite 300), Knoxville (800 S Gay St, Suite 700), London (162-168 Regent Street), Johannesburg (22 Kildoon Rd, Bryanston), Cape Town (31 Brickfield Road, Woodstock) and China (No. 1 Ningzhou Road, Wuxi). Regions: USA | AFRICA | UK | UAE | CHINA. ISO 9001 and ISO 45001 certified.
Reserve and load shedding questions
How much spinning reserve does a mine power station need?
At least the output of the largest loaded engine, so one trip can be covered without dropping load. Many mines add a margin for the largest motor start.
Does a stopped standby engine count as spinning reserve?
No. Only unused output on engines that are already running and synchronised helps in the first seconds after a trip.
What is under-frequency load shedding?
It is a protection scheme that disconnects blocks of load in a fixed order when frequency falls below set thresholds, so the remaining engines can hold the grid.
Which mine loads should never be shed?
Underground ventilation, dewatering, hoists carrying people, refuge chambers, station auxiliaries and control systems should stay on supply.
Can a battery reduce load shedding at a mine?
Yes. A battery can supply power within a second of a trip, giving HFO engines time to pick up load and reducing how often shedding operates.
How often should a load shedding scheme be tested?
At commissioning and after any change to engines, large motors or feeders, with relay checks at regular maintenance intervals.
Review your station reserve
Send your single-line diagram, engine list and mine load schedule, and our engineers will review your reserve rule and shedding stages and suggest where the margin is thin.
You can reach the engineering desk on +27 10 822 2324, send drawings or data sheets to info@uspeglobal.com, or leave the details on the station reserve review request. Additional HFO generating sets to raise running reserve are listed in our current equipment stock.