Mining power guide

Mine Power Purchase Agreements for HFO Power Stations in Africa

A mine that needs 20 to 60 MW of baseload power far from a reliable grid has three broad choices: build and run its own HFO station, pay a contractor to build and run one, or let an independent producer own the plant and simply buy the electricity. The third route is governed by a power purchase agreement, and the way that agreement is written decides who carries fuel risk, breakdown risk and the risk that the mine closes early.

This guide walks through the structure of a mine power purchase agreement for an HFO engine station: the ownership models, the parts of the tariff, how fuel and efficiency are handled, what availability really means in contract terms, and the clauses that protect both sides over the life of the mine.

Why a mine may prefer to buy power

Mining companies raise capital to develop orebodies, not power stations. Taking a 40 MW HFO plant off the balance sheet frees money for the pit, the plant and the tailings facility, and it moves the specialist job of running medium-speed engines to a party that does it every day.

The trade-off is control and long-term cost: the producer prices in its capital, risk and margin. The decision usually turns on how certain the mine life is and how much operating risk the board wants to keep.

Three ownership models compared

In the owner-operated model the mine contracts an EPC builder, takes over the station at handover and staffs it itself. In the EPC plus O&M model the mine still owns the plant but a contractor runs it under performance targets. In build-own-operate, or build-own-operate-transfer where ownership passes to the mine at the end of the term, the producer owns everything inside the fence and sells energy across a meter.

Each model moves risk differently. A useful exercise is to list the main risks, such as construction delay, engine failure, fuel price, fuel quality, currency, load shortfall and early mine closure, and mark who carries each one under each model. The agreement then has to reflect that allocation clause by clause.

How the tariff is built

Most mine power purchase agreements split the tariff into a capacity charge and an energy charge. The capacity charge pays for the plant being available whether or not the mine draws power, and recovers the producer’s capital, fixed O&M and return. The energy charge pays for each kilowatt-hour delivered and covers fuel, lube oil, consumables and variable maintenance.

Splitting the tariff this way protects the producer against the mine running at low load during a mill shutdown, and protects the mine against paying for fuel it never used. Indexation clauses then adjust each part for inflation, currency and fuel price on an agreed formula, so neither side has to reopen the agreement every time markets move.

Who buys the fuel and who carries efficiency risk

On many mine stations the mine already runs a fuel supply chain for its haul fleet, and some choose to buy HFO directly and deliver it to the producer. Others leave fuel procurement to the producer and pay for it through a pass-through in the energy charge. Either way, the agreement must state who carries the risk of a fuel shortage, a quality failure or a late delivery convoy.

Efficiency is usually handled through a guaranteed specific fuel consumption. Suppose the producer guarantees 210 grams of fuel per kilowatt-hour and the station delivers 200 GWh in a year. If actual consumption runs at 218 grams, the extra 8 grams per kilowatt-hour adds up to 1,600 tonnes of fuel. Under a well-written agreement that excess is the producer’s cost, which gives it a direct reason to keep injectors, turbochargers and separators in good order.

Availability guarantees in practice

The capacity charge is normally tied to an availability guarantee, often measured as the share of hours in which the contracted capacity was ready to run. Planned maintenance agreed in advance is usually excluded, while forced outages count against the producer. If availability falls below the guarantee, the capacity charge is reduced on a sliding scale.

Define capacity at the mine’s point of connection, not at the alternator terminals, so that transformer and switchgear failures count too. Our article on adding engines in stages explains why an N+1 or N+2 engine count is the practical way a producer meets an availability guarantee on a remote site.

Minimum offtake and the life of mine

A producer financing a station needs to know it will be paid long enough to recover its investment. That leads to minimum offtake or take-or-pay clauses and to a term that matches the expected life of mine. The difficulty is that mine plans change with commodity prices and drilling results, and a ten-year agreement on a mine that closes in six leaves someone with a stranded plant.

Good agreements address this openly. A termination schedule sets out what the mine pays if it closes early, usually declining over time as the producer’s capital is recovered, and often gives the mine the option to buy the station at a scheduled value. Because engine plant can be dismantled and moved, a relocation clause that lets the producer take the engines to another site can reduce the termination payment.

Planning for load growth and grid arrival

Mines rarely stay the same size. A concentrator expansion or a new underground section can add 10 MW within a few years. The agreement should give the mine the right to request additional capacity on pre-agreed terms, including how the new engines will be priced and how quickly they must be installed.

Grid arrival is the opposite case. If a transmission line reaches the mine, the station may move from baseload to standby or peaking duty. Writing that scenario into the agreement, with a revised tariff for reduced running hours, avoids a dispute later.

Payment security, step-in and fuel reserves

Producers and their lenders will ask for payment security, typically a letter of credit or parent company guarantee covering several months of tariff. In return the mine should ask for step-in rights that let it, or a nominated operator, run the station if the producer fails to perform.

A minimum fuel stock obligation is just as important on an inland site. The agreement should state how many days of full-load fuel the producer must hold on site, how that stock is verified and what happens if a road closure or port delay draws it down. Our wider guide to HFO station delivery and operation covers storage and tank farm sizing in more detail.

A checklist before signing

Before signing, confirm that the contracted capacity and the guaranteed availability are measured at the same point; that the fuel quality specification matches what the supply chain can actually deliver; that the efficiency guarantee states its reference conditions; that planned outages are scheduled around mill shutdowns; and that the termination schedule reflects a realistic mine plan rather than the most optimistic one.

Finally, make sure the O&M obligations are specific on staffing, spares, overhaul intervals, reporting and environmental monitoring.

About the authors

This guide comes from the USP&E commercial engineers and station managers who structure, build and operate HFO power stations supplying African mines under contract. USP&E is an EPC and O&M contractor, not a broker, with 150+ power projects in 45+ countries, 25,000 MW contracted since 2002 and 24+ years in the field. Our power station EPC projects cover owner-operated, contractor-operated and producer-owned arrangements.

Offices: Colorado Springs (1755 Telstar Dr, Suite 300), Knoxville (800 S Gay St, Suite 700), London (162-168 Regent Street), Johannesburg (22 Kildoon Rd, Bryanston), Cape Town (31 Brickfield Road, Woodstock) and China (No. 1 Ningzhou Road, Wuxi). Regions: USA | AFRICA | UK | UAE | CHINA. ISO 9001 and ISO 45001 certified.

Mine PPA questions

What is a mine power purchase agreement?

It is a long-term contract under which an independent producer owns and runs a power station and sells electricity to a mine at an agreed tariff, with set rules on availability, fuel and term.

What is the difference between a capacity charge and an energy charge?

The capacity charge pays for the plant being ready to run and recovers fixed costs. The energy charge pays for each kilowatt-hour delivered and mainly covers fuel and variable maintenance.

Who should carry fuel efficiency risk?

Normally the producer, through a guaranteed specific fuel consumption. Fuel used above the guarantee is the producer’s cost, which gives it a reason to keep engines well maintained.

What happens if the mine closes before the agreement ends?

A termination schedule sets the payment due, usually reducing over time. Many agreements also let the mine buy the station or let the producer relocate the engines.

How is availability measured in a mine PPA?

Usually as the share of hours the contracted capacity was ready at the point of connection, excluding agreed planned maintenance but including forced outages.

Can a PPA allow for mine expansion?

Yes. A well-drafted agreement gives the mine the right to request extra capacity on pre-agreed pricing and installation terms.

Test your power purchase structure

Share your load forecast, mine plan and fuel arrangements, and our engineers will help you compare owner-operated, contractor-operated and producer-owned options for an HFO station.

You can reach the engineering desk on +27 10 822 2324, send drawings or data sheets to info@uspeglobal.com, or leave the details on the mine power enquiry form. HFO engines and generating sets suitable for mine stations are listed in our power equipment inventory.


Where we operate

USA | AFRICA | UK | UAE | CHINA

USP&E United States

Colorado Springs Office: 1755 Telstar Dr, Suite 300

Knoxville Office: 800 S Gay St, Suite 700

USP&E South Africa

Johannesburg Office: 22 Kildoon Rd, Bryanston

Cape Town Office: 31 Brickfield Road, Woodstock

USP&E United Kingdom

London Office: 162-168 Regent Street

USP&E China

China Office: No. 1, Ningzhou Road, Wuxi

Call:+27 10 822 2324  |  E:info@uspeglobal.com

ISO Certifications
ISO9001ISO45001

Powering Possibility. Built for the Frontier.
Full-service EPC & O&M. Not a broker.

© 2026 USP&E · Africa Generators is part of USP&E