This guide walks through the fuel side of an inland HFO plant: how much fuel the station really needs, how it travels from the import terminal, how it is received, heated and stored, and how many days of stock a mine should hold before the supply chain becomes the weakest part of its power system.
Start with the consumption arithmetic
Every logistics decision follows from daily fuel burn. A medium speed HFO engine typically uses somewhere around 200 to 215 grams of fuel per kWh at good load. A station averaging 30 MW of output therefore burns roughly 6.3 tonnes an hour, or about 150 tonnes a day. Allow for station auxiliaries, start-ups and lower efficiency at part load, and the planning figure rises further.
Convert tonnes into trucks. A road tanker carrying around 30 to 35 tonnes means five or more arrivals every day of the year for that example station. That number drives the size of the unloading bay, the queue space at the gate, the staffing of the fuel team and the stock the site must keep in reserve.
From import terminal to mine gate
Most inland mines receive HFO through a coastal terminal, then by road, rail or a combination. Rail is cheaper per tonne and easier on roads, but it needs a siding, heated rail tank cars or reheating at the transfer point, and a reliable rail operator. Road haul is more flexible and is the usual starting point for a new station.
Map the full corridor before signing a supply contract: terminal opening hours, weighbridges, border crossings, steep grades, river crossings and towns with heavy truck restrictions. Each one adds hours, and the total transit time sets how much fuel is always in the pipeline rather than in the site tanks.
Keeping the fuel warm enough to move
HFO is thick at ambient temperature and has to be heated to flow. Tankers are usually insulated and fitted with heating coils or connections for steam or hot oil at the receiving end. On a long haul through cool highland nights, fuel can arrive well below its pumping temperature.
The receiving station therefore needs a way to reheat tanker contents before unloading, typically through a heating connection and enough time at the bay. If this is undersized, trucks queue, drivers exceed their hours and the supply plan falls apart even though the fuel physically reached site.
Receiving, sampling and unloading
Each delivery should be checked before it enters the tanks: paperwork against the order, seals intact, quantity by weighbridge or dip, and a sample drawn for density, viscosity, water and sediment checks. Retain a sealed sample from every load so that any later engine problem can be traced back to a specific delivery.
Unloading pumps, strainers and hoses should be sized for the worst-case viscosity, not the brochure figure. A spill kit, bunded unloading slab and a drain to an oily water separator protect the site and the community water supply, which matters a great deal on a mine permit.
Heated bulk storage and stock days
Bulk storage tanks hold the station’s strategic reserve and are heated and insulated to keep the fuel pumpable. The key policy number is stock days: how many days of full-load running the site can sustain with no deliveries at all. Inland mines commonly plan for somewhere between 15 and 30 days, depending on corridor risk.
Stock days should be set by looking at real disruption history: the longest border closure, the longest road outage in the wet season and the longest terminal shortage in recent years. If the station is expected to grow, as described in our page on expanding an HFO station in phases, size the tank farm footprint for the final capacity even if fewer tanks are built at first.
Fuel handling inside the fence
From the bulk tanks, fuel moves to settling and service tanks, through centrifugal separators that remove water and solids, and then to booster modules that heat it to injection viscosity and deliver it to the engines. Separator capacity, heater duty and spare separators should be designed with the same care as the engines themselves.
Poor fuel handling shows up as injector wear, sticking fuel pumps and liner damage. Our wider guide to HFO station EPC and operations explains how the fuel treatment train fits into the overall plant design and maintenance plan.
Wet season, borders and other corridor risks
Rains can close unsealed roads for days, damage bridges and slow tankers to walking pace on passes. Border posts can stop trucks for documentation, holidays or disputes. Both are predictable in pattern even if not in exact timing, so the stock policy should rise ahead of the wet season.
A practical approach is to build stock steadily in the dry months, agree priority loading with the supplier before the rains, and keep a diesel fallback for black start and critical loads. Diesel day tanks and transfer arrangements are covered in our article on fuel tanks for African generator sites.
Contracts and who owns the fuel chain
The mine, the fuel supplier, the haulier and the O&M contractor each control part of the chain, and gaps between them cause most outages. The supply contract should define quality specification, delivery temperature, minimum and maximum delivery rates, and what happens when trucks are delayed.
Inside the fence, one party should own fuel receipt, storage, handling and the stock reporting that tells the mine when reserves are falling. In most cases that is the O&M contractor running the station, with a daily stock and consumption report shared with the mine’s supply team.
About the authors
This guide comes from the USP&E power station engineers and O&M managers who design HFO plants and run fuel systems at remote mine and utility sites. USP&E is an EPC and O&M contractor, not a broker, with 150+ power projects in 45+ countries, 25,000 MW contracted since 2002 and 24+ years in the field. Our station operations and maintenance services include fuel receipt, storage and stock reporting.
Offices: Colorado Springs (1755 Telstar Dr, Suite 300), Knoxville (800 S Gay St, Suite 700), London (162-168 Regent Street), Johannesburg (22 Kildoon Rd, Bryanston), Cape Town (31 Brickfield Road, Woodstock) and China (No. 1 Ningzhou Road, Wuxi). Regions: USA | AFRICA | UK | UAE | CHINA. ISO 9001 and ISO 45001 certified.
HFO fuel logistics questions
How much HFO does a mine power station use per day?
A medium speed HFO engine uses roughly 200 to 215 g per kWh at good load, so a station averaging 30 MW burns about 150 tonnes a day before allowing for auxiliaries and part load.
How many days of HFO stock should an inland mine hold?
Most inland mines plan for 15 to 30 days of full-load running, set by the longest likely road, border or terminal disruption on their corridor.
Why does HFO need to be heated during transport and storage?
HFO is too viscous to pump at ambient temperature. Tankers, storage tanks and pipework are heated so the fuel can be unloaded, transferred and treated.
Is rail or road better for moving HFO to a mine?
Rail is cheaper per tonne on long hauls but needs a siding and heated tank cars. Road is more flexible and is the usual choice for a new station.
What checks should be done on each HFO delivery?
Check paperwork and seals, confirm quantity, and sample for density, viscosity, water and sediment. Keep a sealed retained sample from every load.
Who should manage fuel at a mine power station?
The O&M contractor running the station usually owns receipt, storage, handling and daily stock reporting, working to a supply contract held by the mine.
Plan the fuel side of your HFO station
Share your site location, expected load and current supply route, and our engineers will review fuel demand, storage and stock-day options with you.
You can reach the engineering desk on +27 10 822 2324, send drawings or data sheets to info@uspeglobal.com, or leave the details on the project enquiry form. HFO engines and balance of plant are listed in our power generation equipment stock.