A mine in Africa rarely has a strong grid behind it. The power station is often the only source on site, it runs in island mode, and it has to ride through mill starts, crusher trips and the odd lightning strike without dropping the plant. Gas turbines suit that duty when the fuel, the air and the people around them are managed properly.
Most of the problems that take a mine turbine offline are not exotic. They come from wet or dirty fuel gas, dust on the inlet filters, hot thin air at altitude, weak protection settings, and spares that are three weeks away by road in the rainy season. Each section below takes one of those topics and sets out what to check, what to plan for and what evidence to keep.
Use the contents list to jump to a topic, or read it top to bottom as a checklist for a new station, an expansion or a plant you have just taken over.
In this guide:
- The path in three stages
- Fuel-Gas Scrubbing
- Load Rejection
- Island-Mode Operation
- Mill Motor Starting
- Altitude Derate
- Grid Code and Islanding
- Station Closure and Redeployment
- Outage Planning with Mine Shutdowns
- Station Expansion and Tie-In
- Site Security and Theft Control
- Community Power Sharing
- Spares Depot Planning
- Sizing for the Life of the Mine
- Rainy Season Access Planning
- Dust Inlet Filtration
- Step-Up Transformer Care
- Lightning Protection
- Water Scarcity Cooling
- Instrument Air
- Vibration Trips
- Fuel-Gas Dewpoint
- Inlet Fogging
- Fire Protection
- How USP&E Supports Mine Power Stations
The path in three stages
- Know the site. Gas quality, dust load, altitude, water and the mine’s load profile set the size and the auxiliaries of the station before any machine is chosen.
- Match the machine to the duty. A remanufactured GE Frame 6B, a used or new gas turbine, or a hybrid plant with engines and storage is judged on island-mode stability, fuel and how it recovers from a load rejection.
- Plan for the life of the mine. Spares depots, outage windows aligned with mine shutdowns, expansion tie-ins and redeployment at closure belong in the plan from day one.
Fuel-Gas Scrubbing
Start With What Is Really in Your Gas
Collect gas analyses over time, not just one sample: composition, water and hydrocarbon dew points, liquids carryover, solids, sulphur compounds and how all of these change with season, supplier and upstream offtakes. CNG and wellhead supplies swing more than pipeline gas, so plan for the worst week, not the average.
Compare that data against the turbine fuel specification. The gap between what arrives and what the turbine accepts defines your treatment train: knockout drums for slugs of liquid, coalescing filters for fine aerosols, particulate filters for solids and heaters to keep gas above its dew point all the way to the fuel nozzles.
Design the Scrubbing Train for Remote Operation
Remote mines need treatment that runs with little attention. Use duty and standby filter vessels so elements can be changed without stopping the turbine, automatic liquid drains with high-level alarms, and differential-pressure indication your operators can read from the control room. Size heaters so gas superheat holds even on cold nights and at low flow.
Put gas quality alarms, filter differential pressure and drain status on SCADA beside the turbine screens. Write a short fuel shed table so non-essential gas users drop first if supply quality or pressure falls.
Load Rejection
Know What Each Drive Can Shed
Start with a load list that shows every large drive on the island bus and the megawatts it sheds when it trips. Mill motors, ball mills, crushers, pump stations and conveyors are the usual suspects, and two of them can trip together when a shared feeder or a process interlock acts.
Measure real demand, not nameplate. Your largest credible rejection is often a combination event, such as a mill trip that also stops the pumps feeding it. Write that case down, because it drives every setting that follows.
Compare that rejection with the number of units online at light and heavy load. A rejection that is easy with four machines running can push a two-machine night shift past its limits.
Check Governor, Fuel Valve and Overspeed Settings
Your gas turbine generators answer a load rejection through the governor and the fuel valves. If the governor is slow or the valves stick, speed overshoots and the overspeed trip acts. If the trip is set too tight, healthy machines drop out at the moment you need them most.
Review governor gains, droop, fuel valve stroke times and overspeed set points against the largest credible rejection. Check that every unit on the bus shares the shock instead of one machine taking it alone.
Look at load-shedding in reverse as well. A rejection is often followed by a restart of the same drive, so your units must accept the load back without a second trip.
Island-Mode Operation
Design Your Island Before You Choose Turbines
Your islanded station has to hold frequency and voltage while mills, conveyors and hoists step on and off. That means governors, excitation, spinning reserve, load-shed tables and black-start sequences belong in the same design file as the machine choice. Packaged gas turbine generators that look right on a datasheet can still trip when a large mill motor restarts after a fault.
Mill Motor Starting
Know What Each Large Start Does to Your Bus
Start with a list of every large motor on the mine: mills, crushers, conveyors, slurry and water pumps, compressors and ventilation fans. Record the rating, the starting method and how often each one starts. Many mines added motors over the years without anyone checking the combined effect on the power station.
Then run a motor starting study for the islanded station. Model the real number of turbines that will be online, not the full installed fleet, and include the generator and excitation data. The study shows how far the voltage dips, how long it takes to recover and whether the turbine governors can hold frequency through the load step.
Check the worst cases. A start during a turbine outage, a restart after a plant trip, and two motors starting close together are the moments that cause blackouts. If your station cannot ride through them on paper, it will not ride through them on site.
Choose the Right Starting Method for Each Drive
Direct online starting is simple but draws the most current. Soft starters lower the starting current but still load the bus, and variable speed drives can bring a mill up gently but add harmonics that the station must handle. Other methods, such as reduced voltage starting through a transformer or a slip-ring motor with resistors, still run on many older African mines.
Pick the method per drive, based on what the study shows and what the process needs. A large mill with a gearless drive or a variable speed drive behaves very differently from a pump that starts direct online. Each choice changes the protection settings and the size of the load step your turbines see.
Altitude Derate
Size Your Station to the Air You Actually Have
Every turbine loses output as altitude rises and ambient temperature climbs, because the compressor moves less mass of air. Your design file should state site elevation, the hottest credible ambient, inlet filter losses and humidity, then convert nameplate ratings into a summer capability curve. That curve, not the brochure figure, is what your load-shed table and spinning reserve must be built around.
Grid Code and Islanding
Let Grid Code and Island Mode Decide Your Design
Start with the facts of your connection: the utility’s fault level at your point of supply, voltage and frequency ranges, how often the feeder trips and how long outages last. Ask the utility for its grid code requirements on ride-through, reactive power and protection. Weak grids amplify every motor start, so a study of your largest loads starting on a weak feeder is essential.
Then decide how your plant should behave when the grid fails. Most mines want the turbines to separate cleanly and keep critical loads running in island mode. That needs a fast, reliable islanding scheme, governors and voltage regulators tuned for isolated operation and a load-shed table that drops non-essential loads before frequency collapses.
Station Closure and Redeployment
Plan Closure Power Years Ahead
Start with the mine plan. Ask when mining stops, when processing stops, and what load stays on site for water treatment, rehabilitation, offices and security. Closure is rarely one day: load usually falls in steps. Map those steps against the station so you know which units must run to the end and which can be released early.
Write this into one closure power plan with dates, unit by unit. It should cover running, maintenance, preservation, transport, permits and staff.
Shut Down, Preserve and Record Every Unit
A gas turbine that stops without preservation can lose value quickly in a hot, humid or dusty climate. Plan each shutdown: run the unit down to the procedure, drain or treat fuel lines, protect lube oil systems, seal inlets and exhausts, fit desiccant where needed, and set a schedule for turning rotors and checking humidity while the unit waits.
Records matter as much as steel. Gather fired hours, starts, trips, inspection reports, borescope images, overhaul history, control software versions and spare parts lists for every unit and auxiliary skid. A buyer or the next mine will pay more for a unit with a clear history, and engineers will plan re-installation faster when they know what they are getting.
Outage Planning with Mine Shutdowns
Build One Calendar for the Plant and the Station
Ask the mine planning team for the shutdown calendar for the next two years, including the long reline stops and the short weekly maintenance windows. Then list every turbine inspection and overhaul that falls due in the same period, worked out from fired hours, starts and trips rather than from the calendar alone. Put both on one chart that everybody can see.
Look for the natural matches first. A combustion inspection may fit inside a mill reline, while a major overhaul may need the longest stop of the year. Where a turbine inspection falls between shutdowns, ask whether it can move a little earlier or later within the limits your maintenance plan and the turbine supplier allow. Small moves often save a whole extra stop.
Plan Parts, Tools and Crews Around Remote Lead Times
Remote mines live and die by logistics. Hot-section parts, gaskets, filters, special tools and lifting gear may need to clear customs, cross borders and travel the last stretch on poor roads. Build your order dates backwards from the outage start, add margin for the rainy season and border delays, and track every critical item on a weekly list until it is on site.
Specialist crews need the same planning. Turbine technicians, borescope inspectors and generator specialists are often booked months ahead, and they need visas, site inductions and medicals before they can start. Agree crew dates early and confirm them again a month before the stop.
Freeze the outage scope at a fixed point before the stop. New items found after the freeze go through a short review: is it safe to defer, does it change the duration, are the parts on site? Scope that keeps growing is the most common reason outages overrun, and on a mine an overrun stops the plant.
Station Expansion and Tie-In
Survey What the Existing Station Can Take
Start with the load case. Ask the mine planning team when the new load arrives, how it ramps and which loads are critical. Then check whether the station needs more firm capacity, more spinning reserve or both. That answer sets the number and size of the new units, and it tells you whether a phased addition makes sense.
Next, survey the station itself. Check the space for new units and their auxiliaries, the capacity of the fuel gas supply and the header, the number of spare bays in the switchgear, the rating of the busbars and step-up transformers, and the cooling and ventilation. Each of these can quietly limit the expansion. A station that has space for two more units but a fuel header sized for the original fleet is not ready to grow.
Design the Tie-In for Short, Planned Outages
Every connection to the live station is a risk, so design the tie-in to need as few outages as possible. Pre-fabricate fuel gas spools, pre-install cable trays and pre-wire control panels while the station runs. Where you can, connect new equipment to isolated spare bays or new branches so the main bus stays live. Group the live tie-in jobs so they fit into the shortest number of agreed windows.
Protection and controls need equal care. New units change fault levels, load sharing and the trip logic of the whole station. Update the protection study, check breaker ratings against the new fault levels and plan how the station control system will see and share load with the new units. Test the new settings on paper and in simulation before anyone touches a live relay.
Site Security and Theft Control
Know What Thieves Target on Your Station
Start with a plain list of what can walk off site: fuel in tanks, day tanks and tankers; copper in power cable, earthing grids and busbars; batteries from the DC system and from vehicles; hand tools, test kit and small spares from stores. Talk to your security team and your plant operators, because each sees different losses.
Then look at how theft actually happens. Fuel is often lost at transfer points, through tampered meters or short deliveries, not by someone climbing a fence. Cable theft usually hits runs that are long, dark and rarely inspected, such as feeders to pump stations or the camp. Stores losses tend to follow weak issue records rather than break-ins.
Spares Depot Planning
Rank Your Parts: Critical, Insurance and Consumable
Start by ranking every part you could need. Consumables such as filters, gaskets and oil are used on a schedule and should always be on site in quantity. Critical spares are parts whose failure stops a unit and whose lead time is long: igniters, fuel valves, control cards, bearings and seals. Insurance spares are the expensive, rarely needed items such as a rotor or a generator exciter, where one failure without a spare could cost you months.
Rank each part by consequence of failure, lead time and likelihood. A simple matrix shows you which items must sit in your site store, which can sit in a regional hub and which can be sourced when needed. Review the ranking every year as your fleet, suppliers and routes change.
Sizing for the Life of the Mine
Start From a Year-by-Year Load Curve
A single maximum-demand figure is not a design basis. Break your load into its drivers: the processing plant and its expansions, pit or underground dewatering, ventilation that grows with depth, hoisting, workshops, and the camp and town supply. Then place each driver on the mine schedule, year by year, so you can see when demand rises, when it plateaus and when it starts to fall toward closure.
Include the awkward loads. Large mill motors and conveyor starts set your transient requirements, and dewatering often runs continuously even when the plant is down. Ask your planners for low, base and high cases, because a feasibility study’s base case rarely survives the first years of operation unchanged. The spread between those cases is exactly what your phasing has to absorb.
Rainy Season Access Planning
Map the Routes That Fail First
Mark the weak points on one map and give each a likely closure time. A low-water crossing that closes for two days a month is a stock problem. A road that closes for six weeks is a design problem, and it may justify a second route, an airstrip upgrade or a larger fuel farm.
Treat the station and the mine as one supply system. The trucks that bring reagents and consumables to the process plant compete with your fuel tankers for the same road on the same dry days. Agree priorities before the rains so power never waits behind a load of cement.
Dust Inlet Filtration
Size Your Inlet Filtration to Pit Dust
Start by measuring the dust you actually have: particle size, concentration, seasonal storms, wind direction from haul roads and crushers, and humidity that can turn fines into cake. Those numbers decide the filter class, the number of stages and whether you need self-cleaning pulse filters, weather hoods, inertial separators or coalescers in front of the fine filters.
Place the inlet away from crushers, stockpiles and haul roads, and raise it above the worst dust layer if you can. Seal the inlet house carefully, because a small bypass leak lets unfiltered air reach the compressor no matter how good the filters are. Your filter choice and inlet location belong in the same design file as your turbine selection. Plan filter access and storage too, because changing elements in a dust storm without a safe platform is how corners get cut.
Step-Up Transformer Care
Know the Condition of Every Step-Up Transformer
Start with a register. For each step-up transformer, record the nameplate data, year of manufacture, cooling type, tap changer type, last oil test and every repair on file. Many mine stations inherited their transformers from earlier projects, and the history sits in several archives or nowhere at all.
Use an accredited laboratory and send samples the same way each time. On a remote mine, courier delays and poor sampling bottles can spoil results, so train one or two people to take samples properly and log the conditions on the day.
Lightning Protection
Turn Your Storm Season Into an Engineering File
Start your lightning protection plan with your own facts, not habit: local strike density, the height of stacks and inlet houses, the length of overhead lines into the pit and the location of every control panel. A rolling sphere or protection-angle study then shows where air terminals and down-conductors belong, and which structures sit inside the protected zone without extra hardware.
Your lightning boundary also has to reach beyond the turbine hall. Conveyor drives, pump stations, camp feeders and radio masts often share earth paths with the generation yard. If those paths are not mapped and bonded, a strike on a distant mast can still travel back into protection relays and trip gas turbine generators that were never hit directly.
Water Scarcity Cooling
Let the Water Balance Choose Your Cooling Architecture
Start with a water balance before you choose a machine. List borehole yields across wet and dry seasons, process-water reclaim, camp demand and any community allocation, then subtract what the plant already uses. What remains is the real makeup budget for cooling, lube oil coolers, evaporative inlet cooling and washing, and it is often far smaller than a vendor datasheet assumes.
With that number fixed, compare dry air-cooled heat exchangers, hybrid wet-dry cells and closed-loop radiators. Dry systems use almost no water but need more plot area and fan power, and they lose capacity on the hottest afternoons. Hybrid cells save water most of the year and switch to spray only at peak ambient. Your gas turbine generators should be rated against the cooling you can actually sustain, not the wet nameplate.
Instrument Air
Size Instrument Air Around Turbine Duty, Not Habit
Start with a demand table for every pneumatic consumer your gas turbine generators will add: fuel and bleed valves, purge systems, inlet filter pulse cleaning and any air-operated dampers. Add the existing plant ring, then size receivers so the turbine can ride through a compressor changeover without a pressure dip that its controls will notice.
Dryer duty matters as much as compressor capacity. Hot, humid pit seasons push moisture into lines, and desiccant towers that were adequate for a crusher plant can fall behind once turbine valves start cycling. Specify the dew point class you need at the turbine skid, not at the compressor house, and give the turbine a dedicated header or priority valve so plant leaks cannot starve it.
Vibration Trips
Map Sensors and Baselines Before You Touch Setpoints
Start with a sensor map for all the gas turbine generators on your island bus. List each proximity probe, seismic sensor and accelerometer, where it sits, what it measures and which channel it feeds. Many mine stations find dead channels, swapped cables or probes that were bypassed during an old repair and never restored.
Then build a baseline at start, idle, part load and full load. Vibration on a turbine changes with speed, temperature and load, so one number on a sheet tells you very little. Record 1x, 2x and broadband levels on each bearing so you know what normal looks like on your machines, not on a brochure.
Repeat the baseline in the hot dry season and the wet season. Dust loading on inlet filters, cooling-water temperature and foundation moisture all shift the picture, and your bands should reflect the conditions your plant actually sees.
Fuel-Gas Dewpoint
Sample Dewpoint Where the Turbine Actually Sees Gas
Sample at the skid inlet and after every heater stage, not only at the pipeline custody point. Many mine stations find the custody meter looks dry while the turbine inlet still carries fog after a long uninsulated run.
Your gas turbine generators need a clear margin above the coldest night and the wettest supplier batch you expect. Record dewpoint with load, ambient and heater outlet temperature so you know what normal looks like on your island, not on a brochure.
Repeat the campaign in the wet season and the dry season. Condensate behaviour changes with both, and your alarms should reflect the conditions your plant actually sees.
Inlet Fogging
Map Inlet Air Before You Spray Water
Map inlet air temperature, humidity and compressor discharge limits for every mine gas turbine on the island bus. Brochure curves from sea-level sites will not protect your altitude pad.
Your gas turbine generators need fogging or evaporative stages sized for the hottest dry week you can prove, not the average day. Record ambient, inlet and discharge together so you know what normal looks like on your island.
Repeat the campaign across wet and dry seasons. Fogging that works in one season can flood drains or starve water quality in another.
Fire Protection
Map Where Fire Can Start on Your Station
Walk the station with a simple question: where do fuel, heat and air meet? On gas turbine generators the usual answers are lube oil lines near hot casings, fuel gas joints inside the enclosure, oil-filled transformers and cable runs that pass under hot equipment.
Rank each source by how likely it is and how much it would cost you in lost power. A small leak on a lube oil skid outside the enclosure is different from a gas leak inside the turbine compartment, and your protection should reflect that.
Check housekeeping too. Oil-soaked lagging, dust build-up on cable trays and stored drums near the turbine hall turn a small event into a station fire. On a dusty mine site these problems come back quickly, so the walk-down needs to be a routine and not a one-off.
How USP&E Supports Mine Power Stations
USP&E has delivered 150+ power projects in 45+ countries and has 25,000 MW contracted since 2002, much of it for remote industrial and mining sites where the plant has to stand on its own.
We hold 2,000+ MW of new, surplus and used turbines and engines in stock, including GE Frame 6B units for remanufacture, so a mine can match equipment to its load without waiting on a long factory slot. Our 400+ engineers and project managers cover EPCM and O&M, from feasibility through to long-term operation, under ISO-certified management systems.
Our teams work to two ideas: Speed with Excellence and Extreme Ownership. In practice that means one accountable team from the first site visit to the day the station is handed over, with support from our global offices.
Search turbines and engines in stock on the USP&E inventory.
Common questions
Can a gas turbine run a mine in island mode without a grid?
Yes, if the station is sized for the largest load step, the governors and protection are set for island operation, and there is enough spinning reserve or storage to carry a mill start or a unit trip.
What fuel gas checks matter most at a mine site?
Liquids, solids and heavy hydrocarbons in the gas, and the margin between gas temperature and its dewpoint. Scrubbing, filtration and heating are set from a real gas analysis, not a design-basis assumption.
How does altitude affect turbine output?
Thinner air reduces the mass flow through the machine, so output falls as elevation and temperature rise. The station has to be sized on site conditions, not on the nameplate rating.
How much dust protection does a mine turbine need?
Enough inlet filtration for the dust load in the dry season, with a filter change and pressure-drop routine that the site team can actually keep up.
What happens to the plant when the mine closes?
A well-documented station can be preserved, moved and redeployed. Keeping maintenance records and spares lists up to date makes that far easier.
Where can I see available equipment?
Search the USP&E inventory linked on this page, or talk to an engineer about the load you need to cover.
Plan Your Mine Power Station with an Engineer
Share your load profile, fuel gas analysis and site conditions, and an engineer will set out the station options that fit the mine.