Mining power guide

Power for Heap Leach Gold Mines in Africa: Loads, Supply and Phasing

Heap leaching has made many lower-grade African gold deposits worth mining, because it avoids the large grinding mills of a conventional carbon-in-leach plant. The power picture changes with it. A heap leach mine still needs crushers, conveyors and a recovery plant, but its largest continuous loads are pumps that move solution across the pad day and night, every day of the year.

That profile matters when the mine is far from a reliable grid and must generate its own electricity. This guide works through the loads of a typical heap leach operation, explains how they grow from first ore to steady state, and sets out the supply choices an owner has when planning an on-site station.

How a heap leach load differs from a milling plant

In a conventional gold plant the ball and SAG mills dominate everything: they set the station size, the motor-starting duty and the protection settings. Heap leach operations replace those mills with crushing, sometimes a drum step that binds fine ore with cement or lime, and a pad where ore is stacked and irrigated with a dilute leach solution. The demand is therefore smaller for the same tonnage, but it is spread across more motors and runs around the clock.

The result is a flatter, steadier curve with a high load factor. That is good news for engine-based stations, which run most efficiently near a constant output, but it also means the plant has very few quiet hours in which maintenance can be carried out without affecting production.

Crushing, ore preparation and stacking

Primary, secondary and sometimes tertiary crushers are the largest single motors on most heap leach sites. They often run on one or two shifts rather than continuously, which creates a daily step in demand when the circuit starts and stops. Conveyors, ore-binding drums and mobile stackers add further load that follows the crushing schedule.

Because crushers start against heavy inertia, the station must be able to absorb a large motor start without voltage dips that trip other equipment. Soft starters or variable speed drives on the largest motors, and a defined start sequence agreed with the process team, make a noticeable difference to the size of generation needed.

Solution pumping: the load that never stops

Barren solution is pumped to the irrigation network on top of the heap, and pregnant solution drains to ponds before being pumped to the recovery plant. These pumps run continuously, and if they stop for long the heap chemistry, pond levels and water balance all start to drift. In the wet season, storm water management can add further pumping that must be available at short notice.

Treat solution pumps as a protected tier in the station design. They should be among the last loads shed in an under-frequency event and the first restored after a blackout, with enough spare generating capacity that one engine can be out for service without forcing them off.

Carbon plant, electrowinning and the gold room

Pregnant solution usually passes through carbon columns, where gold loads onto activated carbon. The loaded carbon is then stripped in an elution circuit, regenerated in a kiln and returned. Elution heaters, kilns, electrowinning rectifiers and the smelting furnace are smaller in total than the crushing circuit, but they are batch loads with sharp steps and, in the case of rectifiers, harmonic content.

Ask early whether elution heating and the regeneration kiln will be electric or fuel-fired, because that choice can move the station size more than any other single decision in the recovery plant. Harmonic studies for rectifiers and drives should be done with the generator impedance, not only the grid case.

Building the load profile over the life of the mine

Heap leach mines rarely reach full demand on day one. Early months may run only part of the crushing circuit and a small irrigated area, while later years add pad extensions, longer pumping distances and higher lifts as the heap rises. Plot the demand year by year, then size the first phase of generation for the early profile with space, foundations and switchgear ready for later units.

Our page on choosing new or refurbished HFO engines explains how engine condition affects that phased approach, especially where the mine life is uncertain.

Supply options for remote sites

Most remote heap leach operations choose between high-speed diesel sets in containers, medium-speed engines burning heavy fuel oil, gas engines where pipeline or trucked gas exists, and hybrid plants that add solar and batteries. High-speed diesel is quick to deploy and easy to relocate. Medium-speed HFO engines cost more to install but usually suit long mine lives with a steady load.

The steady, round-the-clock profile of heap leaching also suits solar with storage, because daytime solar can cut engine fuel use while the batteries help with crusher starts. The engines remain the backbone of supply at night and in poor weather, and the controls must keep them above minimum load when solar output is high.

Reliability, redundancy and water

Plan the station so that the loss of the largest running unit does not stop solution pumping. On a small site that may mean N+1 engines; on a larger one, N+2 allows one unit to be in overhaul while another fails unexpectedly. Keep critical pump motors on separate feeders so a single cable fault cannot stop both duty and standby pumps.

Power and water are linked on these sites. Engine cooling, dust suppression and process water all compete for the same supply, so choose radiator cooling where water is scarce and agree the cooling design with the site water balance before the engines are ordered.

Operating the station through the mine life

Once running, the station needs planned overhauls timed around crushing campaigns, a stock of critical spares and operators who understand the process priorities. Linking the station control system to the plant control room lets operators see which loads are running and plan engine starts around crusher schedules.

Many owners choose a long-term operations contract so that one party answers for availability. The questions to ask in that contract are covered in our article on mine power station O&M terms.

Review the mine location and operating conditions with our Africa generation team before finalising the equipment and support plan.

Who prepared this guide

Mining power is the work our Johannesburg and Cape Town engineers do most often: they plan, build and run generation for processing plants and pads across the continent. USP&E takes contracts as the delivering EPC and O&M company, not as a broker, and brings 150+ power projects in 45+ countries, 25,000 MW contracted since 2002 and 24+ years of site experience to each design. Our approach to project delivery is outlined on the power plant EPC projects page.

Offices: Colorado Springs (1755 Telstar Dr, Suite 300), Knoxville (800 S Gay St, Suite 700), London (162-168 Regent Street), Johannesburg (22 Kildoon Rd, Bryanston), Cape Town (31 Brickfield Road, Woodstock) and China (No. 1 Ningzhou Road, Wuxi). Regions: USA | AFRICA | UK | UAE | CHINA. ISO 9001 and ISO 45001 certified.

Heap leach power questions

Does a heap leach mine need less power than a milling plant?

Usually yes for the same tonnage, because there are no large grinding mills. The demand is steadier, though, because solution pumps and the recovery plant run around the clock.

Which heap leach loads should be protected first?

Solution pumps, pond and storm water pumps, and the carbon plant come first, because stopping them disturbs heap chemistry and the water balance. Crushing can usually restart later.

Can solar power a heap leach mine?

Solar with batteries can supply a large share of daytime energy, but engines or another firm source are still needed at night and in poor weather. The controls must keep running engines above their minimum load.

How should generation be phased for a heap leach project?

Size the first phase for the early pad and crushing profile, and leave space, foundations and switchgear for later units as pumping distances and lifts increase.

Plan the power for your heap leach operation

Send the process flow sheet and a draft motor list, and our engineers will help build the load profile and compare supply options for each phase of the mine.

Our engineers take enquiries by telephone on +27 10 822 2324, by email at info@uspeglobal.com and through the mining enquiry form. Engines and generating sets that may suit a first phase are listed in our equipment inventory.


Where we operate

USA | AFRICA | UK | UAE | CHINA

USP&E United States

Colorado Springs Office: 1755 Telstar Dr, Suite 300

Knoxville Office: 800 S Gay St, Suite 700

USP&E South Africa

Johannesburg Office: 22 Kildoon Rd, Bryanston

Cape Town Office: 31 Brickfield Road, Woodstock

USP&E United Kingdom

London Office: 162-168 Regent Street

USP&E China

China Office: No. 1, Ningzhou Road, Wuxi

Call:+27 10 822 2324  |  E:info@uspeglobal.com

ISO Certifications
ISO9001ISO45001

Powering Possibility. Built for the Frontier.
Full-service EPC & O&M. Not a broker.

© 2026 USP&E · Africa Generators is part of USP&E